If your Nottingham home has a driveway, garage or other off-street parking, you almost certainly do not need planning permission to install an EV charger — a wall-mounted chargepoint serving an area lawfully used for off-street parking is permitted development. The work is still notifiable under Part P of the Building Regulations, your electricity network operator still has to be told, and anyone renting or holding a lease needs written consent before anything is fitted. Permission is really four questions folded into one: planning, building control, the electricity network, and whoever owns the building or the land you park on. The installations that stall almost always stall on the last. Do I need planning permission to install an EV charger? In most cases, no. Class D of Part 2 of Schedule 2 to the Town and Country Planning (General Permitted Development) (England) Order 2015 grants permitted development rights for the installation of an electrical outlet mounted on a wall for recharging electric vehicles, within an area lawfully used for off-street parking. A standard 7kW wall box serving a driveway or garage sits squarely inside that, and Class E covers a free-standing upstand where there is no suitable wall. Permitted development is not the same as no rules applying — the right is conditional, and a minority of properties fall outside it. One restriction worth knowing about has gone. Until 2025 a chargepoint could not be installed under permitted development where it would face onto and sit within two metres of a highway, which ruled out many short front driveways on Nottingham's terraced and inter-war streets. The Amendment Order 2025 (SI 2025/560) removed that for Classes D and E from 29 May 2025, so advice given a few years ago is worth testing again. Which Nottingham properties still need to check with the council? Permitted development rights are restricted in a handful of situations: • Listed buildings. Listed building consent applies separately, and Class E excludes an upstand within the curtilage of one. • Scheduled monuments. Both classes exclude a chargepoint within a designated site. • Conservation areas. Rights are usually tightened rather than removed, and it can turn on where the unit is visible from. • Article 4 directions and planning conditions. Some estates have had rights withdrawn — visible in the planning record, not on the house. The check costs nothing. Mapperley sits across the Nottingham City and Gedling Borough boundary, and the two have separate planning departments, so establish which one your street falls under. Does an EV charger installation need Building Regulations approval? It needs notification, which is not the same as approval in advance. A chargepoint runs on its own new circuit, and adding a circuit to a dwelling in England and Wales is notifiable under Part P. Either an electrician registered with a competent person scheme such as NAPIT self-certifies and notifies building control for you, or the work is notified before it starts. This is not work for a householder. It means a new circuit from the consumer unit and a specific earthing arrangement, both covered by Section 722 of BS 7671, and it must be installed and tested by a qualified, registered electrician. You should end up holding an Electrical Installation Certificate and a Building Regulations compliance certificate — a conveyancing solicitor will ask for both. Does the electricity network operator need to be told? Yes, and it is the installer's job rather than yours. The distribution network operator owns the supply up to your meter; for Nottingham and the East Midlands that is National Grid Electricity Distribution. The installer assesses whether your supply can carry the extra load alongside everything else in the house, and the installation is then either notified after connection or applied for in advance. A supply already close to its limit is a common reason a job turns out bigger than expected. Do I need my landlord's or freeholder's permission? If you rent, yes — in writing, before anything is booked. A chargepoint permanently alters the building and its wiring, and no reputable installer will fit one on a tenant's say-so. If you own a leasehold flat, the lease decides. Most contain a qualified covenant against alterations — consent required but not prohibited — and where that is so, section 19(2) of the Landlord and Tenant Act 1927 implies that consent cannot be unreasonably withheld. A refusal resting on appearance alone, or on a blanket no-chargers policy, has been treated as unreasonable, and the First-tier Tribunal (Property Chamber) can determine the point. The exception matters. Where the charger needs land outside your demise — a communal car park, a shared wall, a bay you do not own — section 19 does not apply and consent sits at the landowner's absolute discretion. That is the most common reason a flat installation stops, and beyond reading the lease it is a question for your solicitor, not your electrician. Can I run a charging cable across the pavement? Not as of right, and not with a loose cable or a mat over it. The footway is highway, the trip hazard is real, and the liability lands on the householder. The sanctioned route is a channel set into the pavement with the highway authority's approval. Nottinghamshire County Council runs a cable channel pilot for county residents with no off-street parking at all, fitted free to eligible households through Via East Midlands. It requires a smart chargepoint already installed by an installer authorised by the Office for Zero Emission Vehicles, and Somo is not on that OZEV list. Inside the city boundary the authority is Nottingham City Council, so a city address is a separate enquiry. What should I check before booking an EV charger installation? In the order that saves the most wasted time, stopping where the job becomes an electrician's. • Confirm the parking is genuinely off-street and within your boundary. • Ask the council whether the property is listed, in a conservation area or under an Article 4 direction — and for Mapperley, whether the address is city or borough. • If you rent or hold a lease, get written consent before quotes, and ask about any wall or ground outside your demise. • Photograph the front of your consumer unit. Do not open anything — the outside is all an installer needs. • Have the installer confirm in writing who notifies Part P and who notifies the network operator. Frequently asked questions Can my freeholder refuse permission for an EV charger? Where the lease requires consent but does not prohibit alterations, section 19(2) of the Landlord and Tenant Act 1927 means consent cannot be unreasonably withheld, and the First-tier Tribunal can decide whether a refusal was reasonable. Where the work needs communal land outside your demise, that protection does not apply and the decision is the landowner's. Have your solicitor read the lease. Do I need permission to install an EV charger if I rent my home? Yes. You need the landlord's written permission before work is arranged, because a chargepoint permanently alters the building and its electrical installation. If the landlord holds a lease themselves, they may in turn need the freeholder's consent. Keep a copy — the installer will reasonably want to see it. Is planning permission needed for an EV charger in a conservation area? Often not, but it is the case most worth checking. Rights in conservation areas are commonly tightened rather than removed, and the answer can turn on where the unit would be visible from. An enquiry to the local planning authority settles it at no cost, which is cheaper than moving a charger afterwards. Can I install an EV charger myself? No. A chargepoint is a new circuit run from the consumer unit with a particular earthing arrangement, which makes it notifiable work under Part P and work falling under Section 722 of BS 7671. It has to be installed and tested by a qualified, registered electrician. Fitting one yourself leaves the installation uncertified and puts anyone using it at risk. EV chargepoint installation with Somo Electrical Somo Electrical is a NAPIT-registered contractor installing electric vehicle charging points across Nottingham, including Mapperley . We will tell you whether your supply and parking suit a charger, and say so if a consent needs sorting first. Call 07733 666004 or use the quote form. Our guide to what an EV charger quote should include covers cost, and who can claim the EV chargepoint grant covers funding — Somo is not an OZEV approved installer and cannot apply for or deduct a grant. Sources checked 11 September 2026: the Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 2, Classes D and E; the Amendment Order 2025 (SI 2025/560), in force 29 May 2025; section 19(2) of the Landlord and Tenant Act 1927; Part P and Section 722 of BS 7671; Nottinghamshire County Council's cable channel pilot. Confirm anything you rely on with your local planning authority, GOV.UK or Electrical Safety First. Not legal advice.